Run the job in HHM Core PM and keep approved customer messages with the job in HHM Connect. Keep the estimate, schedule and job records together. HHM runs the ads: each lead goes to one contractor and is never shared.
Built by active general contractors and master tradesmen, from real project management.
Month to month. Cancel anytime.
Portal Basic is free: 3 projects, 3 team seats. Clients, trades and suppliers never use a seat.

Cedar Ridge Construction
Scheduled task → supplier lead time + your extra days → order-by date
Works with
Names and logos belong to their owners. Your plan shows the available connections.
HHM Connect and Core PM
Estimate the work, schedule your crew and track job costs with HHM Core.
Capture the inquiry in HHM Connect. Price and run the job in PM. Keep customer details and conversations beside the project.
The marketing side
Use approved customer texts and project email from PM.
The job side
Build estimates, check takeoff quantities, schedule the crew and share product choices. Keep inspection photos, repairs and closeout files with the job.
HHM Connect keeps customer conversations with the job. Work the inquiry, start the project and build the estimate and schedule.
The same job stays with you from inquiry to closeout.
Your office sees customer history; project managers see assigned jobs. Clients, trades, and suppliers see the details you share.
Review the follow-up HHM Intelligence drafts from the job details before sending.
Read the customer messages help articleFree leads
Free leads. One lead, one contractor, never shared. HHM spends on the ads and offers each lead to one contractor at a time. Leads HHM hasn’t booked are free, no monthly cap, and if you book one yourself, HHM takes nothing. $69 only when HHM already booked the appointment for you.
Your own leads stay yours. Unbooked leads are free, with no monthly cap. Booked leads are $69 only when HHM already booked the appointment.
See the lead programYour office sees the lead. Other people see the job details you share with them.
HHM Intelligence can draft a follow-up. Check the recipient and message before you send it.
Read the lead follow-up help articleWhat contractors tell review sites
Themes from public reviews of construction and marketing software, sampled October 2026. No names, just the problems.
It took weeks to learn.
Each person sees the tools they need. A setup checklist gets your people, projects, and business tools ready.
See the first stepsI can't get my data out.
An administrator or assigned client can choose Export project CSV on the overview. Download signed proposals and the documents shared with you.
Take your data with youThe price keeps changing and clients cost extra.
Every price is published; clients, trades and suppliers never use a seat.
See published pricesPhotos won't upload on site.
Photos shrink before upload and retry; if it fails, yours stays selected.
See photo reviewOur marketing tool doesn't know about our jobs.
HHM Connect keeps the lead, estimate, schedule, and job together in HHM Core PM.
See one systemBased on themes in public reviews on G2, Capterra and Software Advice. These themes cover several products.
Owners and office staff see company work. Other people see assigned jobs and the details you share.
Read the getting started help articleBuilt by builders
HHM Core PM is built by an active general contractor and master tradesmen. Every tool started as a problem on a real job.
The people designing the tools are the ones pricing jobs, scheduling trades and passing inspections.
Late materials, fuzzy proposals, lost photos, leads nobody followed up: each one became a tool.
We run our own jobs on it every day, see what gets in the way and ship fixes as problems come up.
Owners and office staff can review company work. Project managers, homeowners, trades, and suppliers use the views for their role.
Read the projects help articleEvery lead in one place
Add an inquiry in Deals. Open the customer history in Leads and choose the next step.
Next action: book the site visit
Use approved customer messages from PM. See text and email
Explore HHM ConnectYour office sees sales history. Project managers, trades, suppliers, and homeowners see project information you share with them.
HHM Intelligence can draft a follow-up for your review before you send it.
Read the leads and follow-up help articleEstimating
Quantity times unit price, material and labor visible, signed with a typed name.
Willow Creek Residence – Primary bath
Pricing can come from company cost codes, a saved template, your $/sf rate or a reviewed market rate. This proposal uses Cedar Ridge’s cost codes.
Remove the existing fixtures and finishes; protect adjacent rooms.
IncludedProvide a 10-yard container and haul away the demolition debris.
IncludedReplace damaged subfloor areas with plywood ready for finish work.
IncludedAdd fixture backing and frame the shower curb.
IncludedFrame the shower niche and bath partition.
IncludedSupply and fit the shower control valve and finish trim.
IncludedSupply and install the two selected faucets.
IncludedSet the toilet and connect it to the plumbing connections.
IncludedComplete bath supply, drain and fixture connections.
IncludedSupply and install four recessed LED fixtures.
IncludedSupply and install bath ventilation.
IncludedInstall the protected outlets and switches in the bath work.
IncludedComplete wiring and fixture connections for the bath.
IncludedInstall cement-board backing at the shower walls.
IncludedApply the shower waterproofing system before tile installation.
IncludedHang and finish the surrounding drywall surfaces.
IncludedSupply and install the selected bath floor tile.
IncludedSupply and install the selected shower wall tile.
IncludedFinish the niche and tile transitions with trim.
IncludedPrepare and paint the bath walls and ceiling.
IncludedSupply and fit the frameless enclosure to the finished shower.
IncludedAllowances adjust to the actual selections through an agreed change order.
Due at signing
10% of Project TotalPlumbing and electrical rough-in inspections passed
30% of Project TotalTile installed and finish work reviewed
30% of Project TotalFinal walkthrough and agreed punch items complete
30% of Project TotalTotal payments$26,209.17
$932.40 is reserved for concealed conditions and necessary work adjustments. Cedar Ridge manages the reserve with client approval for its use; the unused portion is credited at closeout.
Start an estimate from whatever you have: a starter template, field measurements and photos, a floor plan, a short description or a roof report. You can also start blank. Price it with template prices, your cost codes, a price per square foot or market rate, then pick the finish level. The proposal shows allowances, payment milestones and contingency, and your client accepts or declines item by item and signs with a typed name.
See how estimating worksOffice staff and project managers see estimate work. Homeowners see shared proposals. Trades and suppliers see the project information you share with them.
HHM Intelligence can prepare a draft from job information. Review quantities and pricing before you send the proposal.
Read the quotes and proposals help articleHHM Core Payments
Accept card and bank payments. Card: 3.5% + $0.30. Bank transfer: 0.9% with a $9 minimum. Instant payouts: 1.4%. Payment updates and receipts stay with the project.
Add a lender application link to a quote after you verify its terms with the lender.
Show the work, payment request, and lender information in the project record.
Order materials on time
PM links materials to the schedule tasks that need them and calculates order-by dates from lead time plus your extra days.
Drag to slip the schedule and watch the order date follow.
Order-by dates move with the task. Change any link you want, then review and send each order.
See scheduling and procurementOffice staff and project managers see material plans. Suppliers see their orders. Trades and homeowners see the project information you share with them.
Read the purchase orders help articleQuality and permit inspections
Keep your photo review and repair history beside permit and inspection notices.
Photo → guidance → team decision → repair thread
Photographed from the stair opening; header over the kitchen opening and 16 in. stud spacing.
Guidance for your team. Your team saves the decision.
Inspection email arrives → your team reviews it → team and trade get notified
Your team reviews inspection notices, then the project team and assigned trade get the update through their chosen channels.
Keep the team quality result separate from the permit result: your reviewer decides the repair work; the inspector decides official approval.
See inspectionsOffice reviewers use Inspections. Trades see their inspection and repair work. Homeowners see the project records you share.
HHM Intelligence gives photo guidance. Review it before recording your team's decision.
Read the photo inspections help articleFive dashboards
Give your office the company records they need. Project managers see assigned work. Share proposals and choices with homeowners, work details with trades, and orders with suppliers.



Owners and office staff see company work. Other people see assigned jobs and the details you share.
Read the portal roles help articleRoofing
Upload a supplier report. Check the measurements, create a branded quote and send it for online signing.
Review the report measurements, work and waste, then choose Create quote from this report.
Item decisions, typed-name signature and signed PDF stay with the project.
Unbooked leads are free. HHM-booked leads cost $69: one lead, one contractor, never shared.
See roofingYour staff manages the roof report. Project clients see the reviewed summary.
Read the roof reports help articlePricing
Compare published monthly prices for your crew, with sources you can check.
Portal Basic is free permanently. No card needed. Try any paid plan free for 14 days. Add a card to start; you are not charged until day 15. Month to month. Cancel anytime.
Price transparency
Compare the same team size and monthly billing. We use each company’s lowest published plan with estimates and client e-signature, scheduling, daily logs, change orders, a client portal, and bids. If a vendor does not publish a price, we say so.
| Vendor | Matched plan | Monthly price |
|---|---|---|
| HHM Growth | Growth, unlimited team seats | $197/mo |
| JobTread | Single plan | $299/mo |
| Buildertrend | Quote only | Quote only, no published price |
| Houzz Pro | Pro | $449/mo |
| Procore | Quote only | Quote only, no published price |
| Contractor Foreman | Plus, up to 8 users | $199/mo |
| Includes | HHM Growth | JobTread Single plan | Buildertrend Quote only | Houzz Pro Pro | Procore Quote only | Contractor Foreman Monthly tier by team size |
|---|---|---|---|---|---|---|
| Estimates with e-signature | Yes | Yes | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page |
| Scheduling | Yes | Yes | Not listed on pricing page | Yes | Not listed on pricing page | Not listed on pricing page |
| Daily logs | Yes | Yes | Not listed on pricing page | Yes | Not listed on pricing page | Not listed on pricing page |
| Change orders | Yes | Yes | Not listed on pricing page | Yes | Not listed on pricing page | Not listed on pricing page |
| Client portal | Yes | Yes | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page |
| Bids | Yes | Yes | Not listed on pricing page | Yes | Not listed on pricing page | Not listed on pricing page |
| Clients/trades/suppliers free (no seat) | Yes | Yes | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page |
| Customer messages with the job | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page |
| Free leads (one lead, one contractor, never shared) | Yes | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page | Not listed on pricing page |
HHM Growth is $197/mo with unlimited team seats. Bids start at Growth. HHM Starter is $97/mo and includes the same project tools without bids. HHM Pro adds Council review and Portfolio Risk Radar.
Houzz Pro Teams, from $399/mo with unlimited users, is an alternative to Pro. Teams adds email marketing and a custom website; those do not establish the full marketing bundle listed above.
The table shows only what the checked pricing facts confirm. Confirm a tool with the vendor when it is not listed. Contractor Foreman tiers use its published user caps, but these pricing facts do not confirm feature inclusion. Procore lists annual contracts and does not publish a monthly price.
Prices and terms as published by each vendor on October 5, 2026. Check the vendor's site for current pricing. Sources: HHM pricing, JobTread pricing, Buildertrend pricing, Houzz Pro pricing, Procore pricing, Contractor Foreman pricing.
The account owner manages billing and connections. Office staff and project managers see their work. Homeowners, trades, and suppliers use invitations.
Read the plans and billing help articleBefore you start
What is free, who owns the leads, and how hard it is to switch.
Try any paid plan free for 14 days. Add a card to start; you are not charged until day 15. Month to month. Cancel anytime.
Portal Basic is free permanently. No card needed. Portal Basic includes 3 active projects, 3 team seats, and 80 ready-to-edit starter templates. Sign in from your invitation, add your people, and create your first project. Clients, trades, and suppliers never use a team seat.
No. Add clients, trades, and suppliers in People, assign their role and projects, and send an invitation. They open the records you share with them. Every paid plan includes unlimited team seats.
No. Each lead goes to one contractor at a time, never shared. If you pass, HHM can offer it to the next contractor. Once booked with you, it stays yours. Unbooked leads are free, with no monthly cap. The $69 fee applies only when HHM already booked the appointment.
Leads from your website, ads, referrals, and phone stay yours. Enter an inquiry in Deals or connect your lead source to bring its history into Leads. HHM offers its own advertising leads separately under the lead program terms.
Start with one job. Bring your contact and cost lists, load or create templates, add your people, and enter the project details. Check each import before you share it. Your administrator or assigned project client can choose Export project CSV on the project overview.
Add job details, photos, plans, or a prompt. HHM Intelligence drafts estimates, daily-log recaps, and follow-ups, and highlights issues for review. Check each draft before you use or send it.
Owners set up the company. Office staff manage customers. Project managers run assigned jobs. Homeowners, trades, and suppliers see what you share.
Read the getting started help articleYour next job
Use Portal Basic for your first project. Clients, trades and suppliers never cost a seat. Export a project CSV from its overview.
Month to month. Cancel anytime.
Your administrator sets up the company. Office staff and project managers see their work. Homeowners, trades, and suppliers see what you share.