Construction scheduling software that keeps jobs moving

Keep your schedule beside the scope, people, documents, and field work that shape each next step.

How it works

Plan the dates, assign the crew and track their hours in the same job.

  1. Set the work plan. Enter tasks, dates, dependencies, and assignees in Schedule.

  2. Plan material dates. PM calculates order-by dates from the schedule and supplier lead time.

  3. Record field time. Clock in and out from the project's Time Clock.

  4. Review the work. Review time-clock hours before posting labor to the job.

Read the step-by-step Help Center article

Build a schedule around the work

Put every job step in the order the work needs. Set its start date and owner in Schedule.

See the next due date in the list and the full job on the timeline. The crew calendar shows each person’s active assignments.

Keep the team current when dates move

Link work that must happen in sequence. When a date changes, review the work and people that follow.

Keep the reason for a change with the job. Daily logs, photos, and RFIs give your team the context.

Order materials on time

Link each material group to the scheduled work it supports. PM updates the order-by date when Schedule changes.

Turn reviewed takeoff quantities into material needs. Keep purchase orders, delivery photos, and received quantities with the job.

Keep Schedule useful through closeout

Update Schedule as the job changes. Clients see the items you publish, while the crew sees assigned work.

Start with Portal Basic for three active projects and three team seats. It includes 80 ready-to-edit starter templates.

Willow Creek example

In a Willow Creek remodel, framing starts on Day 52. A material group needs 14 supplier days and 3 ordering days, so PM shows Day 35 as the order-by date. If framing moves to Day 58, PM moves the order-by date to Day 41. Check supplier timing and site readiness before you order.

Frequently asked questions

Can construction schedules change during a job?

Change the task date in Schedule. PM updates linked work and material planning dates so you review the next step.

Who is construction scheduling software for?

Owners and project managers set the schedule. Office and field teams see the work assigned to them. Share the details homeowners, trades, and suppliers need.

Related pages

Keep the job moving

Previous stepVisualization and selectionsNext stepProject managementEvery toolBrowse all tools

Put the next job step in one place

Open your free HHM Core PM account and begin with up to three projects and three seats.

Start free