construction cost code list

Construction cost code list for estimates and job costs

A cost code list gives your estimates, budgets, purchase records, and job reviews the same names for the same work.

How it works

Choose the cost-code structure and units your company will use on every job.

  1. Set the code and unit. Add company cost codes, names, units, and costs.

  2. Use codes on the job. Choose the code and unit in takeoffs, quotes, and budget lines.

  3. Compare job costs. Use budget and report views to compare planned and actual costs by code.

  4. Review the result. Check the code, quantity, and cost before you use it on the project.

Read the step-by-step Help Center article

Track job costs with shared names

Use the same cost-code names for planned and actual costs. Choose codes that match how your team estimates, buys, and reviews work.

Use company cost codes, units, and unit costs in quotes, Budget, and takeoffs. Budget compares planned and actual costs by code.

Start with familiar categories

Use the starter list as a beginning, from general conditions to exterior improvements. It includes categories for sitework, concrete, carpentry, roofing, finishes, plumbing, and electrical.

Pair every item with the right unit. SF measures area, LF length, EA items, CY volume, and SQ roofing.

Make the list fit your company

Review the starter with the people who estimate, buy, supervise, and review costs. Combine items you never separate and add detail where it changes a decision.

Set the unit before entering costs. Clear names make Budget differences easier to understand.

Use the same codes through closeout

Choose the code and unit when you price reviewed quantities. Compare planned and actual costs by that code during the job.

Review the list after closeout. Split unrelated work and remove unused codes from the active list.

Willow Creek example

In a Willow Creek remodel, framing quantities use 06000 Carpentry and fixture counts use 15100 Plumbing. Keeping a unit with every quantity prevents an area measurement from becoming a fixture count. The project manager reviews the related Budget and purchase records under the same codes.

Free contractor download

Download the free cost-code starter CSV

Frequently asked questions

What is a construction cost code?

A cost code names a type of work, such as framing or plumbing. Use the same codes in estimates and budgets so you can compare planned and actual costs by category.

How detailed should a cost code list be?

Start with the categories your office reviews. Try the list on one quote and budget, then add detail where you need it.

Related pages

Keep the job moving

Previous stepPhone, text, email and pushNext stepVisualization and selectionsEvery toolBrowse all tools

Put the next job step in one place

Open your free HHM Core PM account and begin with up to three projects and three seats.

Start free